Project Update #5 - July 27, 2026
Excavation - First-level excavation of the basement is underway, with lagging and walers installed progressively around the west, south, and east walls as the dig advances north. Excavated material continues to be hauled off site.
Record of Site Condition Remediation - Contaminated soil removal within the excavation footprint continues, with third-party inspection and confirmatory sampling ongoing. Remaining impacted material is concentrated on the north portion of the site; completion is anticipated late August.
Site Services - The dewatering well was installed and commissioned.