The project has received a Noise Exemption Permit from the City which permits certain construction works outside of normal construction working hours. These activities will be limited to items such as
Shoring / Excavation - Excavation and shoring were substantially completed in September, with the final lagging installed along the perimeter walls and the shoring contractor demobilizing at month end
Site Condition Remediation - Soil remediation within the excavation footprint effectively wrapped up early in the month, with third-party sampling confirming all areas met the required environmental s