Project Update #6 - August 24, 2026
Site Condition Remediation - Soil remediation within the excavation footprint effectively wrapped up early in the month, with third-party sampling confirming all areas met the required environmental standard.
Site Services / Utilities - The dewatering system continued operating on a temporary basis while a formal discharge agreement was finalized with the municipal water authority. Municipal site services work is mobilizing in the final week of August for sanitary, storm, water and fire line connections.
Waterproofing - Waterproofing beneath the raft slab will begin at the end of the month, starting on the south side of the site.
Crane Erection - The site is being prepared and coordinated across multiple trades to support crane erection, scheduled for mid-September.