Project Update #6 - August 24, 2026

Aug 24
1 min read
  • Site Condition Remediation - Soil remediation within the excavation footprint effectively wrapped up early in the month, with third-party sampling confirming all areas met the required environmental standard.

  • Site Services / Utilities - The dewatering system continued operating on a temporary basis while a formal discharge agreement was finalized with the municipal water authority. Municipal site services work is mobilizing in the final week of August for sanitary, storm, water and fire line connections.

  • Waterproofing - Waterproofing beneath the raft slab will begin at the end of the month, starting on the south side of the site.

  • Crane Erection - The site is being prepared and coordinated across multiple trades to support crane erection, scheduled for mid-September.




 
 

Recent Posts

See All
Project Update #9 - October 19, 2026

The project has received a Noise Exemption Permit from the City which permits certain construction works outside of normal construction working hours. These activities will be limited to items such as

 
 
Project Update #8 - October 5, 2026

Shoring / Excavation - Excavation and shoring were substantially completed in September, with the final lagging installed along the perimeter walls and the shoring contractor demobilizing at month end

 
 
CRANE ERECTION DATE: SEPTEMBER 14

The crane erection is scheduled for September 14th, weather dependent. Rroad and sidewalk disruption should be expected on this date.

 
 