Project Update #6 - August 24, 2026

Aug 24
1 min read
  • Site Condition Remediation - Soil remediation within the excavation footprint effectively wrapped up early in the month, with third-party sampling confirming all areas met the required environmental standard.

  • Site Services / Utilities - The dewatering system continued operating on a temporary basis while a formal discharge agreement was finalized with the municipal water authority. Municipal site services work is mobilizing in the final week of August for sanitary, storm, water and fire line connections.

  • Waterproofing - Waterproofing beneath the raft slab will begin at the end of the month, starting on the south side of the site.

  • Crane Erection - The site is being prepared and coordinated across multiple trades to support crane erection, scheduled for mid-September.




 
 

Recent Posts

See All
CRANE ERECTION DATE: SEPTEMBER 14

The crane erection is scheduled for September 14th, weather dependent. Rroad and sidewalk disruption should be expected on this date.

 
 
Project Update #5 - July 27, 2026

Excavation - First-level excavation of the basement is underway, with lagging and walers installed progressively around the west, south, and east walls as the dig advances north. Excavated material co

 
 
Project Update #4 - July 1, 2026

Record of Site Condition Remediation - Contaminated soil removal within the excavation footprint is ongoing, with third-party inspection and sampling underway. Excavation/Shoring - The shoring and ex

 
 