Record of Site Condition Remediation - Contaminated soil removal within the excavation footprint is ongoing, with third-party inspection and sampling underway.
Excavation/Shoring - The shoring and excavation commenced in June as part of the remediation work.
Site Setup - The site trailer and security cameras are in place, with field operations and site monitoring now active.
All Posts
Record of Site Condition Remediation - Environmental remediation outside the excavation footprint is complete, with soil backfilled and compacted to accommodate the shoring drill rig platform.
Permits Status - The shoring permit has been approved by the City.
Dewatering System - The dewatering system design has been finalized and coordinated ahead of excavation start.
Structural demolition substantially complete - The existing commercial buildings on site have been demolished, with above-grade structures cleared by late April 2026.
Below-grade clearance and foundation removal underway - Excavation crews are actively removing existing building foundations, basement slabs, and buried concrete layers to prepare the site for shoring platform construction.
Site remediation underway - Environmental crews are actively remediating contaminated soil across the site.
Permit issuance expected mid-May - The next permit application is in progress with the City of Toronto, with permit issuance targeted for mid May, 2026.