  • The project has received a Noise Exemption Permit from the City which permits certain construction works outside of normal construction working hours.

  • These activities will be limited to items such as concrete pours which often need to start and end outside of typical hours to allow for safe and acceptable curing times.




  • Shoring / Excavation - Excavation and shoring were substantially completed in September, with the final lagging installed along the perimeter walls and the shoring contractor demobilizing at month end.

  • Forming - Work on the raft slab foundation is ongoing and about two-thirds of it is complete. Forming and concrete for the basement-to-ground floor walls and columns also started and kept advancing.

  • Crane Erection - The tower crane was erected and commissioned in mid-September and is now in service.

  • Waterproofing - Foundation wall waterproofing continued to follow the concrete work as each section was completed.

  • Temporary Power/Hoarding - Temporary power duct work began on College Street, temporary power equipment was set on site, and hoarding and a covered walkway along the street are being installed.




  • The crane erection is scheduled for September 14th, weather dependent.

  • Rroad and sidewalk disruption should be expected on this date.