  • Record of Site Condition Remediation - Contaminated soil removal within the excavation footprint is ongoing, with third-party inspection and sampling underway. 

  • Excavation/Shoring - The shoring and excavation commenced in June as part of the remediation work.

  • Site Setup - The site trailer and security cameras are in place, with field operations and site monitoring now active.





  • Record of Site Condition Remediation -  Environmental remediation outside the excavation footprint is complete, with soil backfilled and compacted to accommodate the shoring drill rig platform.

  • Permits Status - The shoring permit has been approved by the City.

  • Dewatering System - The dewatering system design has been finalized and coordinated ahead of excavation start.




  • Structural demolition substantially complete  - The existing commercial buildings on site have been demolished, with above-grade structures cleared by late April 2026.

  • Below-grade clearance and foundation removal underway  - Excavation crews are actively removing existing building foundations, basement slabs, and buried concrete layers to prepare the site for shoring platform construction.

  • Site remediation underway  - Environmental crews are actively remediating contaminated soil across the site.

  • Permit issuance expected mid-May - The next permit application is in progress with the City of Toronto, with permit issuance targeted for mid May, 2026.