Project Update #4 - July 1, 2026

Jul 2
1 min read
  • Record of Site Condition Remediation - Contaminated soil removal within the excavation footprint is ongoing, with third-party inspection and sampling underway. 

  • Excavation/Shoring - The shoring and excavation commenced in June as part of the remediation work.

  • Site Setup - The site trailer and security cameras are in place, with field operations and site monitoring now active.





 
 

Recent Posts

See All
CRANE ERECTION DATE: SEPTEMBER 14

The crane erection is scheduled for September 14th, weather dependent. Rroad and sidewalk disruption should be expected on this date.

 
 
Project Update #6 - August 24, 2026

Site Condition Remediation - Soil remediation within the excavation footprint effectively wrapped up early in the month, with third-party sampling confirming all areas met the required environmental s

 
 
Project Update #5 - July 27, 2026

Excavation - First-level excavation of the basement is underway, with lagging and walers installed progressively around the west, south, and east walls as the dig advances north. Excavated material co

 
 