Project Update #8 - October 5, 2026
Shoring / Excavation - Excavation and shoring were substantially completed in September, with the final lagging installed along the perimeter walls and the shoring contractor demobilizing at month end.
Forming - Work on the raft slab foundation is ongoing and about two-thirds of it is complete. Forming and concrete for the basement-to-ground floor walls and columns also started and kept advancing.
Crane Erection - The tower crane was erected and commissioned in mid-September and is now in service.
Waterproofing - Foundation wall waterproofing continued to follow the concrete work as each section was completed.
Temporary Power/Hoarding - Temporary power duct work began on College Street, temporary power equipment was set on site, and hoarding and a covered walkway along the street are being installed.